PRIMARY USE: (52) Foundation Only
WORK DESCRIPTION: Early start foundation only permit( from basement parking level P-5 to grade level) for 8--story core and shell office/retail building with 5 levels of subterranean parking.
PERMIT ISSUED: Yes PERMIT ISSUE DATE: 12/17/2014 ISSUING OFFICE: Metro
CURRENT STATUS: Permit Finaled CURRENT STATUS DATE: 07/06/2017

Permit Application Status History
Plan Check Approved 12/17/2014 SAI KWAN KHUM
Issued 12/17/2014 LADBS
Permit Finaled 07/06/2017 SAKO AGHAZARIAN

Permit Application Clearance Information
Address approval Cleared 08/08/2014 VALENTINO PUEBLOS
City owned building/parcel Cleared 08/08/2014 HAROOT AVANESIAN
Encroachment in public way Cleared 08/08/2014 ARMANDO MEDINA
Eng Process Fee Ord 176,300 Cleared 08/08/2014 VALENTINO PUEBLOS
Construction near power lines Cleared 08/11/2014 OSCAR CASTRO
Hydrant and Access approval Cleared 08/13/2014 ROBERT DUFF
CPC Cleared 08/26/2014 VINCENT QUITORIANO
Highway dedication Cleared 08/28/2014 LINDA MARGARET
Permit Cleared 08/28/2014 LINDA MARGARET
Roof/Waste drainage to street Cleared 08/28/2014 LINDA MARGARET
Miscellaneous Cleared 09/03/2014 LINDA MARGARET
Sewer availability Cleared 09/17/2014 DENNIS OROZCO
Low Impact Development Cleared 09/30/2014 AMMAR ELTAWIL
"D" conditions Cleared 10/07/2014 MARITZA PRZEKOP
"Q" conditions Cleared 10/07/2014 MARITZA PRZEKOP
"T" removal Cleared 10/07/2014 MARITZA PRZEKOP
CPC Cleared 10/07/2014 MARITZA PRZEKOP
Site Plan review Cleared 10/07/2014 MARITZA PRZEKOP
ZA Case Cleared 10/07/2014 MARITZA PRZEKOP
ZI Cleared 10/07/2014 MARITZA PRZEKOP
Hist. Property Cntrct Mgr Appr Cleared 10/08/2014 LAMBERT GIESSINGER
Historic monument Cleared 10/08/2014 LAMBERT GIESSINGER
Historical monument Cleared 10/08/2014 JIM URQUHART
Project located in CRA area Cleared 10/08/2014 JIM URQUHART
Transportation Demand Ord. Cleared 10/08/2014 TAIMOUR TANAVOLI
DAS Clearance Cleared 10/09/2014 SAI KWAN KHUM
Bicycle Parking Cleared 10/14/2014 CHRISTINE SOTELO
Fire Marshall Fire Life Safety Cleared 10/15/2014 ANDREW KO
Tract Map conditions Cleared 11/14/2014 HERMAN VAN BUREN
Work Adjacent to Public Way Cleared 12/04/2014 DAVID PEREZ

Licensed Professional/Contractor Information
Architect Information
Proctor, Curtis Robert; Lic. No.: C29637
120 VASSAR DR
C/O HARTMAN & MAJEWSKY DESIGN GROUP
ALBUQUERQUE, NM  87114
Contractor Information
Owner-Builder
  
Engineer Information
Hill, Edward Foster; Lic. No.: GE2126
GEOTECH 439 WESTERN AVE
GLENDALE, CA  91201
Engineer Information
Maingot, Martin Rex; Lic. No.: S5623
1605 ELMWOOD AVE
WILMETTE, IL  60091

Inspection Activity Information

Inspector Information
DAVID BURKHEAD, (213) 276-8147
Office Hours: 7:00-8:00 AM MON-FRI

Pending Inspection Request(s)
  No data available

Inspection Request History
  Footing/Foundation/Slab   07/22/2015   Partial Inspection   SAKO AGHAZARIAN
  Excavation/Setback/Form/Re-Bar   07/24/2015   Partial Approval   SAKO AGHAZARIAN
  Reinforced Concrete Frame   08/28/2015   Not Ready for Inspection   TED RIES
  Footing/Foundation/Slab   08/31/2015   Partial Approval   SAKO AGHAZARIAN
  Deputy Reinf. Concrete   09/09/2015   Approved   SAKO AGHAZARIAN
  Deputy Reinf. Concrete   09/10/2015   Approved   SAKO AGHAZARIAN
  Deputy Reinf. Concrete   09/11/2015   Approved   SAKO AGHAZARIAN
  Footing/Foundation/Slab   09/11/2015   Partial Approval   SAKO AGHAZARIAN
  Footing/Foundation/Slab   09/16/2015   Partial Approval   SAKO AGHAZARIAN
  Footing/Foundation/Slab   09/22/2015   Partial Approval   SAKO AGHAZARIAN
  Deputy Reinf. Concrete   09/23/2015   Approved   SAKO AGHAZARIAN
  Deputy Reinf. Concrete   09/24/2015   Approved   SAKO AGHAZARIAN
  Deputy Reinf. Concrete   09/25/2015   Approved   SAKO AGHAZARIAN
  Deputy Reinf. Concrete   09/29/2015   Approved   SAKO AGHAZARIAN
  Footing/Foundation/Slab   09/29/2015   Partial Approval   SAKO AGHAZARIAN
  Deputy Reinf. Concrete   09/30/2015   Approved   SAKO AGHAZARIAN
  Deputy Reinf. Concrete   10/01/2015   Approved   SAKO AGHAZARIAN
  Deputy Reinf. Concrete   10/02/2015   Approved   SAKO AGHAZARIAN
  Deputy Pre-Stress Concrete   03/14/2016   Approved   SAKO AGHAZARIAN
  Deputy Reinf. Concrete   03/14/2016   Approved   SAKO AGHAZARIAN
  Deputy Pre-Stress Concrete   03/15/2016   Approved   SAKO AGHAZARIAN
  Deputy Reinf. Concrete   03/15/2016   Approved   SAKO AGHAZARIAN
  Deputy Other (see comments)   03/16/2016   Approved   STEPHEN REED
  Deputy Pre-Stress Concrete   03/16/2016   Approved   SAKO AGHAZARIAN
  Deputy Reinf. Concrete   03/16/2016   Approved   SAKO AGHAZARIAN
  Deputy Pre-Stress Concrete   03/17/2016   Approved   SAKO AGHAZARIAN
  Deputy Reinf. Concrete   03/17/2016   Approved   SAKO AGHAZARIAN
  Deputy Pre-Stress Concrete   03/18/2016   Conditional Approval   BARRY SILLS
  Deputy Reinf. Concrete   03/18/2016   Conditional Approval   BARRY SILLS
  Deputy Other (see comments)   03/21/2016   Conditional Approval   STEPHEN REED
  Deputy Pre-Stress Concrete   03/21/2016   Conditional Approval   BARRY SILLS
  Deputy Reinf. Concrete   03/21/2016   Conditional Approval   BARRY SILLS
  Deputy Pre-Stress Concrete   03/22/2016   Conditional Approval   BARRY SILLS
  Deputy Reinf. Concrete   03/22/2016   Conditional Approval   BARRY SILLS
  Deputy Pre-Stress Concrete   03/23/2016   Conditional Approval   BARRY SILLS
  Deputy Reinf. Concrete   03/23/2016   Conditional Approval   BARRY SILLS
  Deputy Pre-Stress Concrete   03/24/2016   Approved   SAKO AGHAZARIAN
  Deputy Reinf. Concrete   03/24/2016   Approved   SAKO AGHAZARIAN
  Deputy Pre-Stress Concrete   03/25/2016   Approved   SAKO AGHAZARIAN
  Deputy Reinf. Concrete   03/25/2016   Approved   SAKO AGHAZARIAN
  Deputy Reinf. Concrete   03/29/2016   Approved   SAKO AGHAZARIAN
  Deputy Other (see comments)   04/12/2016   Conditional Approval   STEPHEN REED
  Deputy Pre-Stress Concrete   04/12/2016   Approved   SAKO AGHAZARIAN
  Deputy Reinf. Concrete   04/12/2016   Approved   SAKO AGHAZARIAN
  Final   06/28/2017   Partial Inspection   SAKO AGHAZARIAN
  Green Building Final   06/28/2017   Approved   WILLIAM ROSE
  Smoke Detectors   06/28/2017   Approved   SAKO AGHAZARIAN
  Final   07/06/2017   Permit Finaled   SAKO AGHAZARIAN